China Harbour and Boskalis ink huge land reclamation contract in Manila Bay

China Harbour and Boskalis ink huge land reclamation contract in Manila Bay

China Harbour Engineering and Dutch dredging company Royal Boskalis Westminster have won a €650m reclamation contract in Manila Bay.

The Pasay Reclamation Development Project in Manila Bay is a new and modern commercial and residential property development to be run by SMPHI. The project involves the reclamation of approximately 360 hectares through the construction of three artificial island according to international standards to ensure a safe living environment. The islands have been designed to withstand potential large earthquakes. In addition, shore protection works are designed to withstand typhoons.

Peter Berdowski, Boskalis CEO: “We are delighted with the award of this large contract from SMPHI. As Boskalis, we have a rich tradition in land reclamation and we look forward to contributing to a modest incremental growth of the Philippines and to protect part of Manila against the effects of climate change. This has always been an important region for Boskalis and through this project, we have secured utilization for the large dredging vessels for the coming years.” 

For the reclamation activities Boskalis will deploy a number of trailing suction hopper dredgers over a period of two years including its mega hopper dredgers. To accelerate the soil settlement, 60,000 kilometers of vertical drains will be installed. The entire reclamation area will be compacted with vibro- and dynamic compaction to ensure soil stability.

The outer perimeter of the islands will be protected with a combination of rock revetment and a concrete wave wall. Preparatory work is scheduled to commence immediately and work on site is expected to start within the first quarter of 2020. The reclamation activities are expected to be completed within three years and the total project duration including land development is five years.

Visit vimeo.com/boskalis/pasay for an animation about the project activities.